Citadel Ultra-Hydro Stop Moisture Vapor Barrier Primer
Primers & Basecoats
Citadel Ultra-Hydro Stop Primer is a professional moisture-vapor-barrier (MVB) primer system designed for use on damp and green concrete prior to resinous floor coatings. The line includes two options to match project conditions: Ultra-Hydro Stop Primer , a two-component, 100% solids epoxy designed
- In stock locally in Oak Forest, IL
- Technical support from experienced installers
- Pickup at our Oak Forest warehouse
Product Details
Citadel Ultra-Hydro Stop Primer is a professional moisture-vapor-barrier (MVB) primer system designed for use on damp and green concrete prior to resinous floor coatings. The line includes two options to match project conditions: Ultra-Hydro Stop Primer , a two-component, 100% solids epoxy designed for high moisture mitigation, and Ultra-Hydro Stop H2O Primer , a two-component, water-based epoxy formulated for early-install schedules and low-odor applications.
Regular (100% solids): self-leveling, fast-setting epoxy primer that provides excellent adhesion and high moisture mitigation—when applied at the specified film build, it reduces vapor emission on moisture-laden slabs (meets ASTM F3010 requirements). H2O (water-based): 50%-solids epoxy primer for moisture control with excellent adhesion to damp concrete; can be applied as early as 48 hours after placement to help reduce job-site downtime.
Recommended Uses
- MVB primer over damp or green concrete prior to epoxy, polyurethane, or polyurea systems (follow approved system guidance).
- Projects requiring strong adhesion and a reliable base for decorative broadcast or high-build systems.
- Accelerated timelines / early installs: use H2O variant for low-odor, water-based application and placement as early as ~48 hours after concrete pour (see TDS).
- High moisture mitigation: use Regular variant where increased moisture vapor transmission (MVT) reduction is required (meets ASTM F3010 when installed to spec).
- Commercial, industrial, and residential substrates where moisture-sensitive coverings or resinous topcoats are planned.
Data sheets and application help
Ask us for the technical data sheet (TDS), safety data sheet (SDS) or application instructions, or call 708-629-0825 to talk through your job.
WARNING: This product can expose you to chemicals known to the State of California to cause cancer and birth defects or other reproductive harm. See www.P65Warnings.ca.gov.
Why Contractors Use It
- Moisture vapor barrier primer that lets resinous coatings go over damp or green concrete
- 100% solids version holds back up to 25 lbs MVT and meets ASTM F3010 at 16 mils
- Self-leveling, fast-setting, single-coat application with excellent adhesion to moisture-laden slabs
- Resistant to high pH; zero VOC
- Water-based H2O version can go down as early as 48 hours after the pour (up to 12 lbs MVT in two coats)
Where to Use It
- Damp, green or moisture-laden concrete before epoxy, polyurethane or polyurea coatings
- Protecting moisture-sensitive flooring
- Pre-tinted colors as a broadcast coat
- Fast-track new construction (H2O version)
How to Apply
- Cure new concrete at least 14 days (100% solids); clean and profile to ICRI CSP 3 (moderate) or CSP 5 (severe service); repair spalls and cracks first
- Precondition parts and room to at least 60°F; apply at 60-80°F with surface 5°F above dew point, out of direct sun
- Power mix (no hand mixing) at 500-750 rpm for 1-3 minutes; partial batches at 1.5:1 base to activator by volume; mix only what you can apply in 25 minutes
- Pour immediately in an 8-12 in. stripe; do not scrape the pail or work from a pan
- Squeegee to 80-100 sq. ft./gal. (minimum 16 mils), back-roll with a 3/8 in. phenolic-core roller, and check wet film thickness; tinting or broadcasting reduces moisture blocking
Coverage & Cure
- Coverage
- 100% solids: 80-100 sq. ft. per activated gallon at a minimum of 16 mils (full 5-gallon kit covers 400-500 sq. ft.; spread rate must be honored). H2O: 250 sq. ft./gal. at 6 mils wet / 3 mils dry (1.5-gallon kit covers 375 sq. ft.)
- Cure and recoat
- 100% solids: working time 25 minutes at 77°F; recoat/topcoat 12-14 hours (scuff sand if over 24 hours); wait at least 24 hours before backer rod and joint sealant. H2O: working time 1 hour at 77°F; recoat/topcoat 5-24 hours (scuff sand if over 24 hours)
- Packaging
- 100% solids 5-gallon kits in Clear (SKU 10301B), Dunes Tan (359081), Light Gray (359082); H2O Primer 1.5-gallon kit, Clear (SKU 10302)
From the manufacturer’s published data (source 1, source 2, source 3). Always follow the current technical data sheet; ask us for the TDS and SDS.
Watch It Applied

Video coming soon
Mixing and application video for Ultra-Hydro Stop. Want to see it in person? It is part of our contractor training.
What Contractors Say About ECM
Ed and his son Matt are phenomenal. The product they sell is top notch and they truly know their craft. Between the great tech help and the great prices this business is the best. I’ve used most coating supply companies in the area over the years and have finally found my forever supplier.
Ultra-Hydro Stop Questions
Where can I buy Ultra-Hydro Stop near Chicago?
Elite Coatings Midwest stocks Citadel Ultra-Hydro Stop Moisture Vapor Barrier Primer at 16410 Kilbourn Ave in Oak Forest, IL, in Chicago’s south suburbs, for pickup. Call 708-629-0825 or request pricing online.
What is Ultra-Hydro Stop used for?
Damp, green or moisture-laden concrete before epoxy, polyurethane or polyurea coatings; Protecting moisture-sensitive flooring; Pre-tinted colors as a broadcast coat; Fast-track new construction (H2O version).
What is the coverage rate of Ultra-Hydro Stop?
100% solids: 80-100 sq. ft. per activated gallon at a minimum of 16 mils (full 5-gallon kit covers 400-500 sq. ft.; spread rate must be honored). H2O: 250 sq. ft./gal. at 6 mils wet / 3 mils dry (1.5-gallon kit covers 375 sq. ft.) (manufacturer’s figure; actual coverage depends on the surface and how it is applied).
How long does Ultra-Hydro Stop take to cure?
100% solids: working time 25 minutes at 77°F; recoat/topcoat 12-14 hours (scuff sand if over 24 hours); wait at least 24 hours before backer rod and joint sealant. H2O: working time 1 hour at 77°F; recoat/topcoat 5-24 hours (scuff sand if over 24 hours) (manufacturer’s figures; times vary with temperature and humidity).